Sometimes a project comes up where while you feel you have all the skills and expertise to build or fabricate the project you just don’t have the historical estimating information to price the job correctly. So what do you do?
The first step is to break down the project into more "handable" discrete parts, in other words create a Work Breakdown Structure (WBS). Perform quantity takeoffs (materials) for each part of the WBS breakdown and then you can do anyone of a number of things….
One of the things you may find is that when you break down the project into lets say for example 5 distinct tasks is that one or two of those task you may then realize is very similar to some other task that you already have historical data for. You can then create a new task item for this new unfamiliar work you are doing based on that historical data which you have then just tweaked up or down a little for this new tasks definition.
Then sit down with your partners and any employees and talk about the time requirements for each component part of the project and see what they think. Your recollections and theirs of similar tasks and their durations can be used to estimate the present task effort and durations. Task Effort and Duration are two different things. You need to know the Effort to set your price since that will be your estimate of how many labor hours you folks actually put into the work while the Duration is how much time it takes up on your schedule. If you have to wait for paint to dry between coats for instance that wont add to the Effort since you are doing nothing or doing something else while your waiting for the paint to dry but waiting for the paint to dry will take up blocks of time on your schedule. It is important to note that all projects are different; each project is affected by different constraints and assumptions, but it many cases this is a fairly accurate method to estimate task duration.
That is very similar to where I mentioned approaching your partners and employees above but is a formal codified approach .
You then plug those values into he formula E = (O + 4M + P)/6 and that give you duration/and/or effort estimate. As I just said too you can do it as a group (maybe the best course given your relative inexperience estimating) and then you’ll use the averages of the three estimates for O, P, and M values.